mark4yesu 8/31/2016 11:51:11 AM

eConnect for GP10 - PO Change Order

Hi,

I have a client using GP10 and want to do PO change orders to update revision numbers and make adjustements to the line items (even cancelling lines if needed).

I don't see how that can be done. Is there a separate proc or do we try to use the the <taPoLine> node?

Any input would be helpful. thanks!

Mark

Version: GP 10
Section: Dynamics GP, eConnect


Table Definition Quick Links
All Tables
SOP Tables
RM Tables
GL Tables
POP Tables
HR Tables
PM Tables
UPR Tables
IV Tables
Olympic Tables